Ready to Fly
|
24 August 2008 |
Final Items Closed Off
|
17 August 2008 |
Crud - Lots and Lots of Crud
|
13 August 2008 |
Cleaning up Loose Ends
|
10 August 2008 |
Final Inspection Done - Finally!
|
09 August 2008 |
First Flight Delay
|
20 July 2008 |
Weight and Balance
|
20 July 2008 |
Fuel Flow Test
|
13 July 2008 |
Fuel Flow Problem Resolved
|
01 July 2008 |
Monday Progress
|
30 June 2008 |
Compass Swing and Radio Checks Completed
|
28 June 2008 |
Engine Start - Finally!
|
27 June 2008 |
Engine Start - Oh So Close
|
22 June 2008 |
Steady Progress
|
01 June 2008 |
Visitor
|
25 May 2008 |
Inverted Oil System Breather
|
25 May 2008 |
Lower Wing Intersection Fairing
|
25 May 2008 |
Brake Fluid
|
25 May 2008 |
Misc Progress
|
19 May 2008 |
Flap Inboard Lower Surface Machinations
|
04 May 2008 |
OAT Probe Working
|
04 May 2008 |
On the road again
|
27 April 2008 |
Fuel Line Rebuilt
|
24 March 2008 |
Progress Again
|
22 March 2008 |
No Progress - Savannah, Snow
|
09 March 2008 |
Pitot Tube Installation
|
24 February 2008 |
Elevator Pushrod Binding Fixed
|
17 February 2008 |
Progress
|
10 February 2008 |
Elevator Pushrod, Flaps, Etc.
|
04 February 2008 |
Right Wing Tip Installed
|
26 January 2008 |
Bell Tail Wheel
|
20 January 2008 |
Left Wing Tip
|
20 January 2008 |
Certificate of Registration
|
14 January 2008 |
Pitot Line Snap Bushing Saga
|
13 January 2008 |
Running the Wing Wires
|
06 January 2008 |
Slow Progress
|
01 January 2008 |
Slow, Cold Progress
|
16 December 2007 |
Wings Mounted
|
09 December 2007 |
Snow
|
04 December 2007 |
Mounting Elevators - Dealing With the Spacers
|
30 November 2007 |
Wing Mounting on Hold
|
30 November 2007 |
Some Days You Should Just Stay in Bed
|
26 November 2007 |
Fuel Tanks, Ailerons, Rudder Mounted
|
25 November 2007 |
Move to the Hangar - More Details
|
18 November 2007 |
Successful Move to the Hangar
|
17 November 2007 |
Fuselage move to the airport - soon, I hope
|
14 November 2007 |
Wings Moved to Hangar
|
28 October 2007 |